油循環(huán)系統(tǒng):在啟動(dòng)前,首先啟動(dòng)油泵控制系統(tǒng),油泵控制系統(tǒng)啟動(dòng)后保證空壓機(jī)各潤(rùn)滑部件潤(rùn)滑良好,同時(shí)油泵控制系統(tǒng)可通過內(nèi)置的溫控閥來調(diào)節(jié)內(nèi)部油壓和油溫,以滿足系統(tǒng)需要。
1. Oil circulation system: before starting, the oil pump control system
should be started first. After the oil pump control system is started,
all lubricating parts of the air compressor can be well lubricated. At
the same time, the oil pump control system can adjust the internal oil
pressure and oil temperature through the built-in temperature control
valve to meet the needs of the system.
2、氣路循環(huán)系統(tǒng):壓縮機(jī)工作時(shí),空氣經(jīng)過自潔式空氣過濾器被吸入,通過PLC自動(dòng)清洗過濾器,空氣在經(jīng)過進(jìn)口導(dǎo)葉自動(dòng)調(diào)節(jié)后進(jìn)入一級(jí)壓縮,經(jīng)一級(jí)壓縮后的氣體溫度較高,然后進(jìn)入中間冷卻器進(jìn)行冷卻(水走管內(nèi),氣走管外,中冷器的水流量要求為110m/h)之后進(jìn)入二級(jí)壓縮系統(tǒng),為避免系統(tǒng)中的氣體倒入壓縮腔內(nèi)(避免帶壓起動(dòng))在壓縮機(jī)的排氣管道安裝有一只懸掛全啟式止回閥,壓縮機(jī)排出的氣體推開止回閥進(jìn)入排氣消聲器,然后進(jìn)入一級(jí)后冷器,二級(jí)后冷器,再進(jìn)入排氣主管道。
2. Air circulation system: when the compressor is working, air is sucked
through self-cleaning air filter and cleaned automatically by PLC. The
air enters the first stage compression after being adjusted by the inlet
guide vane automatically. The temperature of the gas after the first
stage compression is higher, and then it enters the intercooler for
cooling (the water flows in the pipe, the gas goes out of the pipe, and
the water flow of the intercooler is required to be 110m / h) Into the
secondary compression system, in order to prevent the gas in the system
from pouring into the compression cavity (to avoid starting with
pressure), a suspended full open check valve is installed in the exhaust
pipe of the compressor. The gas discharged from the compressor pushes
the check valve open to enter the exhaust muffler, then enters the
primary aftercooler, the secondary aftercooler and then enters the main
exhaust pipe.
3、水路循環(huán)系統(tǒng):冷卻水通過管道進(jìn)入空壓井蓋鋼模具 U型槽模具 天津水處理設(shè)備 檢查井鋼模具 保定公司注冊(cè) u型槽模具 流水槽模具機(jī)中間冷卻器對(duì)一級(jí)壓縮排出的氣體進(jìn)行冷卻降溫,再進(jìn)入后冷器對(duì)排氣進(jìn)行冷卻,另一路冷卻水進(jìn)水管道經(jīng)過主電機(jī)上部的兩組換熱器冷卻電機(jī)繞組,還有一路對(duì)油冷卻器進(jìn)行冷卻。
3. Water circulation system: the cooling water enters the intermediate
cooler of the air compressor through the pipeline to cool the gas
discharged from the first stage compression, and then enters the
aftercooler to cool the exhaust gas. The other cooling water inlet pipe
cools the motor winding through two groups of heat exchangers on the
upper part of the main motor, and another channel cools the oil cooler.